Brucejack Transmission Line: Right of Way ClearingOwner: Pretium
Project Description: R&R Utility was responsible for the Right of Way Clearing for the 56 km long transmission line connecting the new Brucejack Gold Mine to the Long Lake Transmission line. Located about 65 km north of Stewart BC, the right of way crosses some of the most challenging and rugged terrain in BC. The lack of ground access necessitated the use of helicopters to provide transportation for workers, and materials. R&R Utility cleared 245 Hectares, and constructed 100 helipads, all while staying $3 million under budget and finishing ahead of schedule. Services Provided:
|
|